Frank McCoppin Elementary School Remodel Proposition A - San Francisco Year Originally Built: 1975 Sq. Feet of Building: 21,386sf Sq. Feet of Project: 21,386sf Owner: SFUSD Contractor: Thorenfeldt Construction for phase 1 Rose Construction for phase 2 Construction Cost: $365,979 This remodel of an existing 400-student elementary school was divided into two phases. Phase one was required to be completed in three months during summer break, included adding interior walls, new flooring, painting and electrical outlets. Portions of Phase two were completed while the school was occupied and included an outdoor play structure, a disabled access ramp, restroom renovation, fire and life safety improvements, as well as lighting improvements, security fences and other miscellaneous repairs. The work was done in collaboration with Mallas & Foote Architects. Office of Regulation Services (ORS) review and approvals were obtained by Zachary Nathan Architect.